Monte Carlo milestone cones (p10/p50/p80) #10
Notifications
Due Date
No due date set.
Blocks
Depends on
#23 query_project read tool
christian/commitea
#32 Performance pass against the numeric goals
christian/commitea
#7 Lognormal cold-start priors + seedable sampler
christian/commitea
#9 Deterministic scheduler (topo order -> dated plan)
christian/commitea
Reference: christian/commitea#10
Reference in New Issue
Block a user
No description provided.
Delete Branch "%!s()"
Deleting a branch is permanent. Although the deleted branch may continue to exist for a short time before it actually gets removed, it CANNOT be undone in most cases. Continue?
Run the scheduler over N sampled duration draws (priors now, empirical fit later) -> milestone completion-date bands, never point dates.
Acceptance: fixed seed -> stable p10<=p50<=p80; shape matches runway/milestone view contracts (agent-tools.md).
Shipped — Monte Carlo cones (p10/p50/p90) on Focus/Runway/milestone.